Counting pavers looks like simple division, until you add cuts, patterns, curves and broken pieces. Order too few and the next batch may not match in color. This guide shows how to count pavers properly and how much extra to allow.
Step 1: measure the area
Measure the area you will pave, in square feet or square meters. Split curved or L-shaped patios into simple shapes and add them together. Subtract anything inside the patio that will not be paved, such as a fire pit pad or planting bed. See how to measure irregular areas for the formulas.
Step 2: pavers per square foot
Divide 144 (square inches in a square foot) by the face area of one paver in square inches. Use the paver's laying size if the manufacturer lists one, since it includes the joint.
| Paver size | Face area | Pavers per ft² |
|---|---|---|
| 4 × 8 in (brick paver) | 32 in² | 4.5 |
| 6 × 6 in | 36 in² | 4.0 |
| 6 × 9 in | 54 in² | 2.67 |
| 12 × 12 in | 144 in² | 1.0 |
| 12 × 24 in | 288 in² | 0.5 |
| 16 × 16 in | 256 in² | 0.56 |
Many pavers are sold by the square foot or by the layer and pallet, especially multi-size patterns. In that case, skip the per-paver count and order by area plus waste.
Step 3: add a waste allowance
You will lose pavers to edge cuts, cuts around obstacles, breakage and color sorting. Typical allowances:
| Layout | Typical extra |
|---|---|
| Rectangle, running bond or stack bond, few obstacles | 5% |
| Herringbone at 90°, basket weave | 5–10% |
| Diagonal or 45° herringbone | 10–15% |
| Curves, circles, many cut-outs | 10–15% or more |
Diagonal patterns waste more because every edge paver is cut at an angle. Keep a few spare pavers after the job for future repairs; finding an exact color match years later is difficult.
Worked example
A 12 × 16 ft patio with 6 × 9 in pavers in a 45° herringbone:
- Area: 12 × 16 = 192 ft²
- Pavers: 192 × 2.67 = 512 pavers
- Waste at 12%: 512 × 1.12 = 574 pavers (round up)
Laid in a simple running bond, 5% would be enough: 538 pavers. The pattern alone changes the order by about 36 pavers.
Edging
Edge restraint is sold by length. Measure the perimeter that is not against a wall or other fixed edge, then add a little for joins and corners. For a 12 × 16 ft patio against the house on one 16 ft side, the open perimeter is 12 + 16 + 12 = 40 ft.
Joint sand
Joint sand coverage depends heavily on joint width and paver thickness. Narrow joints on large pavers need very little; wide joints on tumbled pavers need much more. Check the coverage chart on the sand bag for your joint width. The patio paver planner lets you enter the coverage from the bag so the count matches your product.
Buying tips
- Buy all pavers from one production run where possible, and mix pallets as you lay.
- Ask whether partial pallets are sold and whether unopened extras can be returned.
- Check the delivery: pallets are heavy and need a firm, level drop point.
Frequently asked questions
How many pavers are on a pallet?
It varies by product. Manufacturers list the square feet and piece count per pallet on the product sheet.
Should I round to full pallets?
Only if partial pallets cost much more. Otherwise, buy your number plus waste and keep the spares.